Electrification of Cranes 7-10
December 20, 2011 Update: After delay in delivery of substation components, the two (2) substation were repaired and have been reinstalled on cranes 9-10 on December 20, 2011.
February 13, 2012 Update: The electrification work on cranes 7 thru 10 is nearly complete to start the commissioning which is being tentatively scheduled to commence on March 5, 2012.