After a competitive selection process was performed, the relocation work was awarded on 5-July-2005 to Noell Konecranes to relocate the three cranes. Crane 1 was the first crane to be removed from service and relocated after which cranes 2 and 3 were relocated individually to Wharf 6. The work lasted approximately four weeks until crane 3 was moved and placed back into operation without any millstones on 2-August-2005.