As we commenced 2019  we are in Highgear working on numerous major PortMiami projects encompassing all aspects of cargo operations including assisting the Port with its cargo terminal relate projects. Some of these projects have been completed such as the Port’s procurement of the Crane Program Engineering Services which was awarded to Paul Bridges and Associated (PBA) and Cranes 4-5-6 Corrosion Repairs and Painting Phase 1. As such, we find ourselves working on numerous projects which are listed below with their status in parenthesis;

  1. Management and Maintenance Initiative Implementation (on-going)
  2. New STS Cranes Procurement (on-going)
  3. Crane Network Connectivity (on-going)
  4. Installation of new StorageTrailer (completed)
  5. Install Pole and US Flag on Crane 10 (completed)
  6. Crane 4-5-6 Refurbishments (on-going)
  7. Management Software Intregration – Mainsaver, RMS and VIAMS (on-going)
  8. Crane Condition Survey and Maintenance Program Upgrades (on-going)
  9. Corrosion Removal and Repairs of Crane 4-5-6 (Interior and Misc) (on-going)
  10. Relocation of Crane 8 (completed)
  11. Electrical Power Relocation and Termination of Gantry Cranes (on-going)
  12. Construction of New Tie Downs for Crane 16 (completed)
  13. Gantry Rail Replacement Phase 2 and 3 (starting)
  14. New Crane Management and Maintenance Facility – Conceptual Design (on-going)
  15. PBB Repairs and Assistance (on-going)
  16. Replacement of Trolley Rails at Hinge area Crane 9 (re-scheduled for Summer 2020)
  17. NDT, Corrosion Removal and Repair of Cranes 7-10 (scheduled for Winter 2019)
  18. Painting of Cranes 7-10 (scheduled for Fall 2020)