The Electrification of Cranes 7-10 Landside Work has commence. The cranes have all the components installed however, they require the Landside Work to be performed to provide the electrical feeds and certain additional Crane Work to make them electrically powered.
The Landside Work is being overseen by the Port’s Capital Develeopment group which contractor was recently issued the Notice to Proceed.
By-weekly coordination meetings are being held to assure the work being performed does not interfere with the Port’s users operations.