Projects

Current

Cranes 4-5-6 Reconditioning and Refurbishment

Cranes 4-5-6 are currently the oldest STS Gantry Cranes at PortMiami which were placed into operations in 1988. In 2005 the cranes were electrified by replacing the diesel generator power by installing new 13.2KV shore power. Soon after, the cranes' drive and...

Management and Maintenance Initiative

As part of the normal operating procedures the Company management commissioned several assessment to include a maintenance audit. Upon the results and its review, the CEO and Board established a framework to develop an action plan and...

Work In Progress

As 2018 commenced we are in Highgear working on numerous major PortMiami projects encompassing all aspects of cargo operations including assisting the Port with its cargo terminal relate projects. Some of these projects have been completed such as the Port's...

New STS Cranes for Port Miami

The New STS Cranes tender for Port Miami solicitation was advertised on February 1, 2018 and proposals were received on April 27, 2018. The tender was posted on BidSync where the Tender Documents, the RFP can be reviewed and downloaded. If there are any questions,...

Completed

New Gantry Cranes 13-16

  Upon issuance of RFP No. 750 by Miami Dade County, evaluation of proposals and recommendation to award, the Board of County Commissioners approved award of Contract No. 750 to Shanghai Zhenhua Heavy Industries Co., Ltd., (ZPMC) on November 15, 2011 for the design,...

Electrification of Cranes 7-10 and Repairs

The 2011 electrification project is designed to complete the Electrification of the Port of Miami Gantry Cranes which project commenced in 2004; known as Phase 1. During Phase 1 the required equipment was mounted and installed on cranes 4-10 but due to scheduling and...

New Cranes 11-12

Several years in the making, cranes 11-12 have been procured by Miami-Dade County Port of Miami to provide its customers with the require service for the new millennium. These cranes are designed with our customer's requirements in mind of their future...

Relocation of Cranes 1, 2 and 3

After a competitive selection process was performed, the relocation work was awarded on 5-July-2005 to Noell Konecranes to relocate the three cranes. Crane 1 was the first crane to be removed from service and relocated after which cranes 2 and 3 were relocated...

Upgrade of Cranes 4-5-6

As cranes 4-5-6 were built in the mid 1980s, the cranes work with outdated analog control drives amongst other components which have reached the end of their efficient work lifespan. As such, Crane Management has scheduled the upgrade of these cranes to digital...

Future Development

SOLICITATIONS

SECURITY