Projects

Current

Cranes 4-5-6 Reconditioning and Refurbishment

Cranes 4-5-6 are currently the oldest STS Gantry Cranes at PortMiami which were placed into operations in 1988. In 2005 the cranes were electrified by replacing the diesel generator power by installing new 13.2KV shore power. Soon after, the cranes' drive and...

Management and Maintenance Initiative

As part of the normal operating procedures the Company management commissioned several assessment to include a maintenance audit. Upon the results and its review, the CEO and Board established a framework to develop an action plan and initiative to address and resolve...

Work In Progress

As we commenced 2019  we are in Highgear working on numerous major PortMiami projects encompassing all aspects of cargo operations including assisting the Port with its cargo terminal relate projects. Some of these projects have been completed such as the Port's...

New STS Cranes for Port Miami

The New STS Gantry Cranes solicitation tender for PortMiami was advertised on February 1, 2018 and proposals were received by April 27, 2018. The tender was posted on BidSync where the Tender Documents and bidding period concluded. As of July 30, 2019, the County's...

Completed

Pressure Clean and Paint Cranes 7, 8, 9 & 10

As Cranes 7-10 had not been re-painted previously, Miami Dade County requested to paint Cranes 7-10 expeditiously including removal of OEM signs and painting the new PortMiami logos. In addition, the crane test weight water tank PMCM logo was painted by the signage...

New Gantry Cranes 13-16

  Upon issuance of RFP No. 750 by Miami Dade County, evaluation of proposals and recommendation to award, the Board of County Commissioners approved award of Contract No. 750 to Shanghai Zhenhua Heavy Industries Co., Ltd., (ZPMC) on November 15, 2011 for the...

Electrification of Cranes 7-10 and Repairs

The 2011 electrification project is designed to complete the Electrification of the Port of Miami Gantry Cranes which project commenced in 2004; known as Phase 1. During Phase 1 the required equipment was mounted and installed on cranes 4-10 but due to scheduling and...

New Cranes 11-12

Several years in the making, cranes 11-12 have been procured by Miami-Dade County Port of Miami to provide its customers with the require service for the new millennium. These cranes are designed with our customer's requirements in mind of their future...

Relocation of Cranes 1, 2 and 3

After a competitive selection process was performed, the relocation work was awarded on 5-July-2005 to Noell Konecranes to relocate the three cranes. Crane 1 was the first crane to be removed from service and relocated after which cranes 2 and 3 were relocated...

Future Development

NOTICES

SOLICITATIONS

WEATHER

Port Readiness Condition:
NORMAL
Crane Readiness Condition:
NORMAL

SECURITY