After a competitive selection process was performed, the relocation work was awarded on 5-July-2005 to Noell Konecranes to relocate the three cranes. Crane 1 was the first crane to be removed from service and relocated after which cranes 2 and 3 were relocated individually to Wharf 6. The work lasted approximately four weeks until crane 3 was moved and placed back into operation without any millstones on 2-August-2005.
NOTICES
SOLICITATIONS
- RFP 2024.01.1a C4-6 and C11-12 OEM Specific Refurbishment and Repairs – Revised
November 22, 2024 2:31 pm
WEATHER
Port Readiness Condition:
NORMAL
Crane Readiness Condition:
NORMAL