by Port of Miami Crane Management | Dec 9, 2009 | News
We moved our Administrative Offices and consolidated Operations at the Field Office facility located at 2886 Port Boulevard. We continue to settle into the new office setup and are making changes to further improve our administrative operations. The principal contact...
by Port of Miami Crane Management | Jun 21, 2009 | News
In a violent storm on Friday afternoon, June 5, 2009 which winds were recorded at 76 mph, cranes 9 and 10 partially derailed as crane 9 collided into crane 10. As such, we implemented emergency procedures and have completed the structural integrity assessment and...
by Port of Miami Crane Management | Nov 20, 2005 | Completed Projects
After contractual agreements were consummated by the Seaport with contractor the electrification of the Port’s gantry cranes 4-10 commenced in July 2004. The civil works commenced first while the crane work was performed by ECC (East Coast Cranes) beginning in...